eServ Home
About eServ
eServ History
Our Customers
The eServ Difference
Lean Engineering
Methodology
eServ eOps Center
eServOnline
Competency Centers
Manufacturing Engineering
Mechanical Design & Analysis
Electrical Engineering
Aerospace Engineering
Project Experience
New Product Introduction
Cost Savings
Redesign
News
Contact Us
Manufacturing Engineering
Industry Solutions
Services & Capabilities
SAP Solutions
Case Studies
Mechanical Engineering
Case Studies
Embedded Engineering
Case Studies
Engine Support
Case Studies
Recent News & Press
BMW launches DriveNow, the 'premium' car sharing service with a Dell Streak on every dash (video)
Read more
News & Events>
Success Stories - Manufacturing
Process Engineering - Cost Reduction
Problem Statement
Need to reduce piece part cost in wheel loader transmission components
Solution
Reviewed part for design modifications based on manufacturing method chosen:
Modified CAD model(s) for geometry changes
Overlay modified part on existing assembly to ensure continued fit and function
Perform FEA analysis as confirmation of continued or enhanced product performance based on geometry modifications & manufacturing method
Evaluated cost benefits of alternate manufacturing process:
Part costs of cost reduction concept vs. current part cost & manufacturing methodology
ROI of initial capital costs based on part cost savings percentage
Results (examples)
Part 1:
ROI of 31 weeks on capital investment (tooling) to alternate process - ROI target <52 weeks
Net savings of 72% in piece part price without loss of part integrity or functionality
Part 2:
ROI of 37 weeks on capital investment (tooling) to alternate process - ROI target <52 weeks
Net savings of 75% in piece part price without loss of part integrity or functionality